محطة كهرباء شمال غزة الفرعية
-
Categoryتوليد الطاقة الكهربائية
-
Clientاي بي بي
-
Supervisorاي بي بي
-
Funded By-
-
RegionNorth Gaza
-
From - To2001-01-01 00:00:00 - 2002-01-01 00:00:00
-
Value0.00$
The work includes
1-construction of control building and transformer foundation, outdoor foundation, cable trenches and. Installation
2-design and installation of plumbing, heating, ventilation, air conditioning, fire detection, lighting and small power.
3-The project includes also all civil and construction works for 640 KVA electrical sub-station. The works also includes installation of heating, ventilation, air conditioning and lighting systems.