Gaza Central Wastewater Project- Reconstruction Program (ER7-4) Rehabilitation Of PS 2 & PS 3
-
CategoryPUMPING STATIONS, SCADA, PLC
-
ClientCMWU
-
SupervisorDORSCH INTERNATIONAL CONSULTANTS GMBH
-
Funded ByKFW
-
RegionGaza City
-
From - To2015-09-01 00:00:00 - 2019-06-01 00:00:00
-
Value900,000.00$
The project is implemented for two sewage Pump Stations PS2 & PS3 in GAZ.A City as Rehabilitation and Fully Reinstallation works
Pumping Station 2
The scope of work is to supply spare part of the following Item
- Lifting equipment - supply and installation
- Ventilation - supply and installation
- Screens
- Standby generator 250 KVA
- Mechanical spare parts
- Electrical spare parts including supply and installation of PLC
Pumping Station 3
The scope of work is to dismantle, supply, install and commissioning the following
- lowing item
- Screen
- Dry well submersible pumps
- Valves & piping
- Ventilation system
- Lifting equipment
- Flow measurement
- Instrumentation & control equipment
- Electrical control panel
- Electrical cabling
- Standby generator
- Fire extinguishers
- Civil engineering materials and metalwork