C1 – Central Gaza WWTP and Wadi Gaza CPS
-
CategoryTreatment Plants
-
ClientCoastal Municipalities Water Utility (CMWU)
-
SupervisorDorsch International Consultants GmbH
-
Funded ByKfW
-
RegionBuriej
-
From - To2016-12-01 00:00:00 - 2020-12-01 00:00:00
-
Value44,089,800.00$
The project works will include:
1. Design and construction of the civil engineering structures and building works, including geotechnical survey on the site of the works.
2. Design, manufacture, transport and erection of mechanical and electrical equipment. Thereafter, testing and commissioning of the facilities as complete functioning works, all in accordance with the project specification.
3. Operation and assistance works for two years after commissioning and issuance of the Taking-Over Certificate.