C6 – Sheikh Ajleen WWTP Measures (Gaza Central Water and Wastewater Project, Contract 6)
-
ClientCoastal Municipalities Water Utility (CMWU)
-
SupervisorCMWU
-
Funded ByKfW
-
RegionGaza City
-
From - To2018-03-04 00:00:00 - 2019-09-08 00:00:00
-
Value999,000.00$
Salfeet WWTP – Design, Construction, Operation and Maintenance, with Solar PV Plant
-
ClientSalfeet Municipality
-
SupervisorGITEC-IGIP GmbH
-
Funded ByKfW
-
RegionSalfeet (West Bank)
-
From - To2017-07-11 - 2024-03-01
-
Value7,075,188.00$
NGEST – Works Completion Contract, North Gaza WWTP (JV Termomeccanica Ecologia / MACC)
-
ClientPalestinian Water Authority (PWA)
-
SupervisorArtelia / MVV-decon / Universal Group / Engicon
-
Funded ByWorld Bank
-
RegionBeit Lahia, North Gaza
-
From - To2016-11-14 - 2018-03-01
-
Value6,285,940.00$
C1 – Central Gaza WWTP (60,000 m³/day) and Wadi Gaza Central Pumping Station
-
ClientCoastal Municipalities Water Utility (CMWU)
-
SupervisorDorsch International Consultants GmbH
-
Funded ByKfW
-
RegionBuriej
-
From - To2016-10-05 - 2022-08-24
-
Value44,089,800.00$
NGEST – Operation and Maintenance of the North Gaza WWTP (JV Termomeccanica Ecologia / MACC)
-
ClientPalestinian Water Authority (PWA)
-
SupervisorArtelia / MVV-decon / Universal Group / Engicon
-
Funded ByWorld Bank
-
RegionBeit Lahia, North Gaza
-
From - To2018-03-01 - 2020-03-01
-
Value6,621,526.00$
NGEST – Supply and Installation of Plant and Equipment, North Gaza WWTP (JV Stulz Planaqua / MACC)
-
ClientPalestinian Water Authority (PWA)
-
SupervisorConsortium Sogreah / MVV Consulting / UG / Engicon
-
Funded ByWorld Bank
-
RegionBeit Lahia, North Gaza
-
From - To2010-05-30 - 2014-09-24
-
Value40,167,000.00$
Gaza Central Wastewater Treatment Plant (Sheikh Ajleen WWTP) – C2: Civil Works
-
ClientCoastal Municipalities Water Utility (CMWU)
-
SupervisorDorsch International Consultants GmbH
-
Funded ByKfW
-
RegionGaza City
-
From - To2010-09-01 00:00:00 - 2012-09-01 00:00:00
-
Value7,630,000.00$
Gaza Central Wastewater Treatment Plant (Sheikh Ajleen WWTP) – C1: Material Supply
-
ClientCoastal Municipalities Water Utility (CMWU)
-
SupervisorDorsch International Consultants GmbH
-
Funded ByKfW
-
RegionGaza City
-
From - To2010-03-01 00:00:00 - 2012-02-01 00:00:00
-
Value11,800,000.00$
NGEST – Terminal Sewage Pump Station (NGEST-NCB-01-04)
-
ClientPalestinian Water Authority (PWA)
-
Supervisor
-
Funded ByWorld Bank
-
RegionBeit Lahia, North Gaza
-
From - To2009-01-01 - 2010-06-30
-
Value3,769,535.00$